Automated Tasks - Monthly schedules set to the 31st

Objective


Understand when an Automated Task scheduled for the 31st runs in months with fewer than 31 days.

Solution


When an Automated Task for Post Tuition Fees or Process ePayments is scheduled to run monthly on the 31st, Jackrabbit automatically adjusts the run date to the last day of months with fewer than 31 days.

  • 31-day months: The task runs on the 31st.
  • 30-day months: The task runs on the 30th.
  • February: The task runs on the 28th or 29th, depending on the year.

For example, a task scheduled to run monthly on the 31st will run on September 30th because September has only 30 days.